Bagged Concrete vs Ready-Mix: Which Should You Use?

For a few post holes, bagged concrete is the obvious choice. For a driveway, a truck is. In between there is a gray zone where the right answer depends on the size of the pour, your access, your crew and local prices. This guide walks through how to decide.

Last updated 2026-11-12

Start with the volume

Everything depends on how much concrete you need. Use the concrete calculator to get the volume in cubic yards and the equivalent number of bags. A handy reference:

ProjectApprox. volume80 lb bags
4 fence posts (10 in hole, 3 ft deep)0.24 cu yd11
4 × 4 ft AC or hot-water-heater pad, 4 in0.20 cu yd9
3 × 20 ft walkway, 4 in0.74 cu yd34
10 × 10 ft patio, 4 in1.23 cu yd56
12 × 20 ft driveway pad, 5 in3.70 cu yd167

Bag counts use the typical 0.60 cu ft yield of an 80 lb bag and include no waste allowance.

The case for bagged concrete

The downside is labor. Each cubic yard is about 45 bags, or 3,600 lb, lifted at least twice: into the vehicle and into the mixer. Mixing by hand in a tub, one or two people can realistically keep up with a small slab, but a large slab can start to set at one end before you finish the other, which leaves cold joints.

The case for ready-mix

The drawbacks are planning and minimums. Suppliers usually charge a short-load fee on small orders, the truck needs firm access close to the pour (or you pay for a pump or line), and you must be fully ready when it arrives because the clock is running.

How to find your break-even point

Prices vary widely by region, so the only reliable way is to get two numbers:

  1. Bag cost: (bags needed × local price per bag) + mixer rental + delivery of the bags if you can't haul them.
  2. Ready-mix cost: call a local supplier and ask for the price per cubic yard, the minimum order, the short-load fee and any delivery or waiting-time charges.

Compare the totals, then weigh the labor. As a rule of thumb many DIYers find bags reasonable up to about one cubic yard and switch to ready-mix or a mix-on-site service above that, but local prices can move that line either way.

A cost worksheet you can fill in

Write down local prices for each line, then total both columns. Leave a line at zero if it doesn't apply.

Bagged concreteReady-mix
Bags needed (incl. waste) × price per bagCubic yards ordered × price per yard
Mixer rental (per day)Short-load fee if below the minimum order
Bag delivery, or trips with your own vehicleDelivery / fuel surcharge
Extra helpersPump or conveyor if the truck can't reach the pour
Wheelbarrow and toolsWaiting time beyond the free unloading period

Worked example with made-up prices

To show how the worksheet works, take a 10 × 12 ft patio at 4 in thick. That is 40 cu ft, or 1.48 cu yd; with 8% waste, 1.6 cu yd or 72 bags of 80 lb mix. Using illustrative round numbers only, not quotes: at $7 a bag plus $60 for a day's mixer rental, bags come to $564. If ready-mix were $160 a yard with a 3 yd minimum, the truck would bill 3 yd ($480) plus, say, a $100 short-load fee, for $580. In that made-up case the totals are close, and the deciding factor becomes labor: 72 bags is about 2.9 tons to lift and mix. Run the same sums with your own local prices; the balance often tips differently from one town to the next.

Mixing bags well

A middle option: rented mixer and a helper

For 20 to 60 bags, a rented electric drum mixer and one or two helpers make bagged concrete practical. Stage the bags next to the mixer, keep a hose ready, and have one person mixing while others place and screed. Pour in sections divided by form boards if you can't finish in one go.

Checklist before any pour

Related reading

Deciding how thick the slab should be changes the volume, and therefore the answer to bags vs truck. See how thick a concrete slab should be. Setting fence posts? Fence post spacing includes a per-post concrete example. For the gravel base, use the gravel calculator or read about gravel types.

Frequently asked questions

How many bags of concrete equal one yard?

45 bags of 80 lb, 60 bags of 60 lb or 90 bags of 40 lb premix make roughly one cubic yard.

What is a short load fee?

Many ready-mix suppliers charge an extra fee for orders below a minimum, often a few cubic yards. Ask for the minimum order and short-load charge when you call for a quote.

Can I rent a mixer for bagged concrete?

Yes. Tool rental shops and some home centers rent electric drum mixers by the day, which makes mixing 20 to 40 bags far more manageable.

Is ready-mix stronger than bagged concrete?

Both can be strong. Ready-mix is batched to a specified strength and mixed consistently, while bagged concrete's strength depends on adding the right amount of water to every batch. Too much water is the most common reason a DIY pour ends up weaker than the bag rating.

How long do I have to work ready-mix?

Not long. Concrete starts to stiffen within a couple of hours of batching, faster in hot weather, so have forms, tools and helpers ready before the truck arrives and ask the supplier about set-retarding options for hot days.